REACH implementation timeline
|
June 01, 2007
|
REACH legislation enters into force Pre-registration phase starts
|
|
June 2008 –
December 2008
|
PRE-REGISTRATION Pre-registration of all phase-in substances supplied at more than 1 tonne per year includes substances that are:
§ EINECS listed (=existing substances)
§ EU manufactured
§ have been existent for 15 years but not yet placed into market
§ No-longer polymers
|
|
December 01, 2008
|
REGISTRATION First phase of registrations Valid for substances supplied at 1,000 tonnes or more and some other priority high-risk substances
|
|
June 01, 2013
|
REGISTRATION Second phase of registrations Must be completed 6 years after REACH comes into force Will apply to substances supplied at 100 tonnes or more
|
|
June 01, 2018
|
REGISTRATION Final phase of registrations for substances supplied at 1 tonne or more
|
|
|
|