REACH implementation timeline

June 01, 2007

REACH legislation enters into force
Pre-registration phase starts

June 2008 –

December 2008

PRE-REGISTRATION
Pre-registration of all phase-in substances supplied at more than 1 tonne per year
includes substances that are:

§  EINECS listed (=existing substances)

§  EU manufactured

§  have been existent for 15 years but not yet placed into market

§  No-longer polymers

December 01, 2008

REGISTRATION
First phase of registrations
Valid for substances supplied at 1,000 tonnes or more and some other priority high-risk substances

June 01, 2013

REGISTRATION
Second phase of registrations
Must be completed 6 years after REACH comes into force
Will apply to substances supplied at 100 tonnes or more

June 01, 2018

REGISTRATION
Final phase of registrations for substances supplied at 1 tonne or more